Verona Airport. Completion of the work of the runway ahead of schedule

Verona, Italy - 58 days of reconstruction for a 16,200 square meters surface

With a few days ahead of time scheduled, on Tuesday May, 10 ended the second phase of the renovation plan of 12% of the Verona's airport runway, 58 days of reconstruction for 16,200 square meters. The new and modern asphalt paving of increased thickness is able to adequately support the take-off and landing of aircraft of increasing weight, in line with the previsions of the plan approved by the shareholders...